Spring loaded safety valve timing check. Regular check

Requirements to protectivevalves

    High reliability.

    Ensuring work stability.

    Fail-safe and timely opening of the valve in case of excess of the working pressure in the system.

    Providing the valve with the required throughput.

    Implementation of timely closing with the required degree of tightness in the event of a pressure drop in the system and maintaining the established degree of tightness with increasing pressure.

Safety valves with spring loading must be manufactured with nominal diameters of the inlet and outlet pipes (DN inlet/DN outlet) 25/40; 40/65; 50/80; 80/100; 100/150; 150/200; 200/300 and nominal pressure of the inlet pipe PN 1.6 MPa, PN 2.5 MPa.

At the pumping station, a special spring-loaded safety valve of the SPPK type, shown in Figure 6.15, has received the widest application.

The technological parameters of the valve are regulated by a ring screwed onto the nozzle. On the top of the ring there is a narrow flat belt. When screwing, the ring approaches the end plane of the plate. By adjusting the gap between the planes of the belt of the ring and the end of the plate, it is possible to regulate the pressure of the full opening of the valve and the pressure of its closing in a wide range, i.e. purge amount.

Installationsafety valves

The installation of safety valves on vessels and apparatus operating under excessive pressure is carried out in accordance with the current regulatory and technical materials and safety rules. Quantity, design, location of valves, the need to install control valves and the direction of discharge are determined by the project.

In any case, the installation of the valve must be provided with free access for its maintenance, installation and dismantling.

When replacing a valve, the flow coefficient of the newly installed valve must not be lower than that of the one being replaced.

Safety valves must be installed in vertical position in the highest part of the vessel in such a way that, in the event of opening, vapors and gases are first removed from the vessel.

On horizontal cylindrical apparatuses, the safety valve is installed along the length of the upper position of the generatrix, on vertical apparatuses - on the upper bottoms or in places of the greatest accumulation of gases.

If it is impossible to fulfill these requirements due to design features, then the safety valve can be installed on a pipeline or a special outlet in the immediate vicinity of the vessel, provided that there is no shut-off device between the valve and the vessel.

Figure 2

1 - body; 2 - nozzle; 3 - spool; 4 - stock; 5 - spring; 6 - screw

On column-type apparatuses with a large number plates (more than 40), if there is a possibility of a sharp increase in their resistance due to a violation of the technological regime, which can lead to a significant difference between the pressure in the bottom and upper parts of the apparatus, it is recommended to install a safety valve in the bottom of the apparatus in the area of ​​the vapor phase of the cube.

The diameter of the fitting for the safety valve must not be less than the diameter of the inlet pipe of the valve.

When determining the cross section of connecting pipelines with a length of more than 1 m, it is necessary to take into account the value of their resistance.

The diameter of the outlet pipe of the valve must not be less than the diameter of the outlet fitting of the valve.

When combining the outlet pipes from several valves installed on one apparatus, the cross section of the collector must be at least the sum of the cross sections of the outlet pipes from these valves.

In the case of combining the outlet pipes of valves installed on several devices, the diameter of the common manifold is calculated from the maximum possible simultaneous discharge of the valves, determined by the project.

The riser, which discharges the discharge from the safety valve into the atmosphere, must be protected from atmospheric precipitation and at the lowest point have a drainage hole with a diameter of 20 - 50 mm for draining the liquid.

The direction of discharge and the height of the discharge riser are determined by the project and safety rules.

The combined collector, which serves for discharges from safety valves into the atmosphere, must be laid with a slope and at the lowest point have a drain with a diameter of 50 - 80 mm with a drain into a drainage tank. "Bags" on such pipelines are not allowed.

The selection of the working medium from the branch pipes and in the sections of the connecting pipelines from the vessel to the valve, on which safety valves are installed, is not allowed.

It is not allowed to install any locking devices, as well as fire fuses between the apparatus and the safety valve.

Heating, cooling, separation and neutralization devices can be installed after the valve. In this case, the total reset resistance should not exceed that specified in paragraph

The resistance of the discharge pipeline of the valve must be no higher than 0.5 kgf / cm 2, taking into account the installation of a separator, heating-cooling devices, neutralization, etc.

At an operating pressure of less than 1 kgf / cm 2, the resistance of the discharge system should not be higher than 0.2 kgf / cm 2.

On devices of continuously operating processes equipped with safety valves, the duration of the overhaul period of which is less than the overhaul period of the installation or workshop, backup safety valves with switching devices can be installed.

In the event that the safety valve is removed for inspection from tanks for storing liquefied gas, or flammable liquids with a boiling point of up to 45 ° C, under pressure, a pre-prepared valve must be installed in its place. It is forbidden to replace the removed valve with a valve or a plug.

Adjustment

Adjustment of safety valves to the pressure of the beginning of opening - the setting pressure (cotton) is made on a special stand.

The set pressure is determined based on the operating pressure in the vessel, apparatus or pipeline.

Working pressure - the maximum excess pressure at which the vessel, apparatus or pipeline is allowed to operate. At operating pressure (P p) the safety valve is closed and provides the tightness class specified in the relevant documentation for the safety valve (GOST, TU).

The set pressure of the safety valve when the discharge is directed from it into a closed system with back pressure must be taken into account the pressure in this system and the design of the safety valve.

The value of the set pressure, the frequency of revision and verification, the installation site, the direction of discharges from safety valves are indicated in the set pressure sheet. The statement is compiled for each installation (workshop) by the head and mechanic (senior mechanic) of the installation (workshop), agreed with the technical supervision service, chief mechanic and approved by the chief engineer of the enterprise.

Each valve body shall be securely affixed with a plate of of stainless steel or aluminum, on which is knocked out:

a) installation site - shop number, conditional name of the installation or its number, designation of the apparatus according to the technological scheme;

b) set pressure - P mouth;

c) working pressure in the apparatus - P p.

The frequency of revision and verification.

On vessels, apparatus and pipelines of oil refining and petrochemical industries, revision and testing of safety valves should be carried out on a special stand with the valve removed. At the same time, the frequency of inspection and revision is established based on the operating conditions, corrosivity of the environment, operating experience and should be at least every:

a) for continuously operating technological production:

24 months - on ELOU vessels and apparatuses, vessels and apparatuses working with media that do not cause corrosion of valve parts, in the absence of the possibility of freezing, sticking and polymerization (clogging) of valves in working condition;

12 months - on vessels and apparatuses working with media that cause the corrosion rate of the material of the valve parts up to 0.2 mm / year, in the absence of the possibility of freezing, sticking and polymerization (clogging) of valves in working condition;

6 months - on vessels and apparatus operating with media that cause the corrosion rate of the material of the valve parts to be more than 0.2 mm/year;

4 months - on vessels and apparatus operating in conditions of possible coking of the medium, formation of a solid deposit inside the valve, freezing or sticking of the shutter;

b) 4 months - for intermediate and commercial storage tanks for liquefied oil gases, as well as flammable liquids with a boiling point up to 45 ° C;

c) for periodically operating productions:

6 months - subject to the exclusion of the possibility of freezing, sticking or clogging of the valve with the working medium;

4 months - on vessels and apparatuses with media in which coking of the medium, formation of a solid precipitate inside the valve, freezing or sticking of the shutter is possible.

The need and timing for checking valves in working condition are determined by the chief engineer of the enterprise.

The value of the corrosion rate of the valve parts is determined based on the operating experience of the valves, the results of a survey of their technical condition during the revision or testing of samples of similar steel under operating conditions.

Checking and revision of safety valves is carried out according to the schedule, which is drawn up in accordance with clause 2.3.1. annually for each workshop (installation), is agreed with the technical supervision service, the chief mechanic and approved by the chief engineer.

The chief engineer of the enterprise is given the right, under his responsibility, in certain technically justified cases, to increase the period of periodic revision of safety valves, but not more than 30% of the established schedule.

Each case of deviation from the audit schedule is documented by an act, which is approved by the chief engineer of the plant.

Valves received from the manufacturer or from reserve storage, immediately before installation on vessels and apparatus, must be adjusted on the bench to the set pressure. After the expiration of the conservation period specified in the passport, the valve must be inspected with a complete disassembly.

Transportation and storage

To the place of installation or repair, safety valves are transported in a vertical position on wooden stands.

When transporting valves, dropping them from a platform of any type of transport or installation site, careless tilting, and installing valves on the ground without linings is strictly prohibited.

Safety valves received from the factory, as well as used safety valves, are stored in a vertical position, packed on linings, in a dry, closed room. The spring must be loosened, the inlet and outlet fittings must be closed with wooden plugs.

Responsible for operation, storage and repair.

Responsible for the installation of the valve after the revision on the relevant devices, the safety of the seals, the timely revision of the valve, the correct maintenance and safety technical documentation, as well as storage of valves in the conditions of the technological workshop is the head of the installation (shop).

Responsible for the storage of valves received for revision, quality audit and repair, as well as the use of appropriate materials during repairs, is the master (head) of the repair shop section.

Responsible for the acceptance of safety valves from repair is the mechanic of the installation (workshop) or the mechanical engineer of the technical supervision department.

Responsible for the transportation of safety valves to the installation site is the mechanic of the installation (workshop). Responsible for the installation is the installation contractor (foreman, head of the repair site).

Revision and repair of safety valves

Revision. Revision of safety valves includes disassembly of the valve, cleaning and troubleshooting of parts, testing of the body for strength, testing of valve connections for tightness, checking the tightness of the shutter, testing the spring, adjusting the set pressure.

Revision of safety valves is carried out in a specialized repair shop (section) on special stands.

Safety valves dismantled for revision must be steamed and washed.

For valves that have been audited and repaired, an act is drawn up, which is signed by the foreman of the repair shop (section), the contractor, the mechanic of the facility where the valves are installed, or the mechanical engineer of the technical supervision department.

Disassembly

The valve is disassembled in the following sequence (Fig. 5.1. Appendix 1):

remove cap 1 mounted on studs above the adjusting screw;

release the spring from tension, for which loosen the lock nut of the adjusting screw 2 and unscrew it to the upper position;

evenly loosen and then remove the nuts from the studs 4 holding the cover 3. Remove the cover. Before removing the cover, apply marks on the flanges of the cover and body or cover, separator and body in case the valve is made with a separator;

remove the spring with support washers 6 and place it carefully in a safe place. It is strictly forbidden to throw the spring, hit it, etc.;

remove spool 7 from the valve body together with the stem and partition, carefully put it in a safe place to avoid damage to the sealing surface of the spool and deflection of the stem.

If there is a separator in the valve, first remove the separator from the body, releasing it from its fastening on the body;

release the locking screws 8 of the adjusting sleeves 9 and 10;

release the guide bush 11 and remove it from the body together with the adjusting bush 9. If the guide bush is firmly seated in the seat of the body, tap the valve body near the guide bush with a hammer to facilitate its release from the body;

remove the adjusting sleeve 10 and the valve nozzle 12. If the sealing surface of the nozzle is slightly damaged, it is recommended that the nozzle be restored without unscrewing the latter from its socket in the body.

Assembly

The assembly of the valve is started after cleaning, revision and restoration of all its parts. The assembly sequence is as follows (Fig. 5.1. Appendix 1):

install the nozzle 12 in the valve body 5, check with kerosene for tightness of the connection between the nozzle and the body; install the adjusting sleeve 10 of the nozzle;

install the guide sleeve 11 with the gasket and the upper adjusting sleeve into the valve body. The hole for the flow of medium in the guide sleeve must be turned towards the discharge pipe of the valve;

install spool 7, connected to the stem, into the guide sleeve;

install partition 13 and separator;

put the spring together with the support washers 6 on the rod;

place the gasket on the adjacent surface of the body and lower the cover onto the body, being careful not to damage the stem. Then center the cover on the boss of the guide bush and fasten it evenly to the studs. Checking the correct installation of the cover is determined by a uniform gap around the circumference between the cover flange and the body.

Before adjusting the spring, you need to make sure that the stem does not stick in the guides. In cases where the spring is freely located in the cover, the stem must rotate freely by hand.

If the spring has a height slightly greater than the height of the cover, and is clamped by it after installation, the check is also made by turning the rod around the axis. The uniform force obtained during the rotation of the stem around its axis will show the correct assembly of the valve;

Create a preliminary tension of the spring with the adjusting screw 2 and finally work it out on the stand;

Install cap 1, tighten the valve nuts.

Figure 2 - Scheme of installation of adjusting bushings.

1 - guide sleeve; 2 - spool; 3 - nozzle; 4 - lower adjusting sleeve; 5 - top adjusting sleeve.

To operate the valve on gas, the adjusting sleeves are installed as follows:

the lower adjusting sleeve 4 must be installed in the uppermost position with a gap between the end face of the sleeve and the valve spool within 0.2 ¸ 0.3 mm;

the upper adjusting sleeve 5 is pre-installed flush with the outer edge of the spool 2; final installation is made in the uppermost position, at which a sharp pop occurs during adjustment on the stand.

When the valve is operating on liquid, the lower adjusting sleeve is set in the lowest position, the upper adjusting sleeve is set in the same way as indicated above.

As a control medium for valves operating on vapor-gas products, air, nitrogen are used; for valves operating on liquid media - water, air, nitrogen.

The control medium must be clean, without mechanical impurities. The presence of solid particles in the test medium can cause damage to the sealing surfaces.

The valves are adjusted to the set pressure by means of an adjusting screw by tightening or loosening it. After each adjustment of the spring, it is necessary to fix the adjusting screw with a lock nut.

Measurement of pressure during adjustment is carried out using a pressure gauge of accuracy class 1 (GOST 8625-69).

The valve is considered adjusted if it opens and closes with a clean sharp pop at a given pressure and using air as a control medium.

When adjusting the valve on liquids, it opens without popping.

Tests

The tightness of the valve plug is checked at operating pressure.

The tightness of the shutter and the connection of the nozzle with the body after adjustment is checked as follows: water is poured into the valve from the side of the discharge flange, the level of which should cover the sealing surfaces of the shutter. The required air pressure is created under the valve. The absence of bubbles within 2 minutes indicates the complete tightness of the valve. When bubbles appear, the tightness of the connection between the nozzle and the body is checked.

To determine the tightness of the connection between the nozzle and the body, lower the water level so that the valve is above the water level. The absence of bubbles on the surface of the water within 2 minutes indicates the complete tightness of the connection.

If the valve does not have tightness in the gate or in the connection between the nozzle and the body, it is rejected and sent for additional revision and repair.

The test of detachable connections of the valve for tightness is carried out in each revision by supplying air to the discharge pipe.

Valves of the PPK and SPKK types are tested with a pressure of 1.5 R at the discharge pipe flange with a holding time of 5 minutes, followed by a decrease in pressure to R y and washing of the detachable connections. Valves with a diaphragm - pressure 2 kgf / cm 2, valves with a bellows - pressure 4 kgf / cm 2.

Hydraulic testing of the inlet part of the valves (inlet pipe and nozzle) is carried out with a pressure of 1.5 R at the inlet flange with a holding time of 5 minutes, followed by a decrease in pressure to R y and inspection.

The frequency of hydrotesting is established by the technical supervision service of the enterprise, depending on the operating conditions, the results of the audit, and should be at least 1 time in 8 years.

The results of valve testing are recorded in the inspection and repair report and the operational certificate.

Valves that have been audited and repaired are sealed with a special seal kept by the repairman. The locking screws of the adjusting bushings, detachable connections body-cover and cover-cap are subject to obligatory sealing.

Troubleshooting and Troubleshooting

Leakage of the medium - the passage of the medium through the valve plug at a pressure lower than the set pressure. Causes that cause an environment leak can be:

the delay on the sealing surfaces of foreign substances (scale, processed products, etc.) is eliminated by blowing the valve;

damage to the sealing surfaces is restored by lapping or turning, followed by lapping and checking for tightness. Lapping eliminates minor damage to the sealing surfaces of the nozzle and spool.

Restoration of sealing surfaces with a damage depth of 0.1 mm or more should be carried out by mechanical processing in order to restore the geometry and remove defective areas, followed by lapping. The repair dimensions of the sealing surfaces of the spools and nozzles are shown in fig. 3.2. The dotted line indicates the configuration of the sealing surface after repair, the numbers indicate the allowable values ​​for which the sealing surfaces can be processed during repair;

misalignment of valve parts due to excessive load - check the intake and exhaust lines, eliminate the load. Make a constriction of the studs;

spring deformation - replace the spring;

opening pressure too low - re-adjust the valve;

poor-quality assembly after repair - eliminate assembly defects.

Pulsation is the rapid and frequent opening and closing of a valve. This may happen for the following reasons:

excessively large valve capacity - it is necessary to replace the valve with a valve of a smaller diameter or limit the lift height of the spool;

narrowed cross-section of the inlet pipeline or branch pipe of the device, which causes the valve to “starve” and thereby causes pulsation - install inlet pipes with a cross-sectional area not less than the area of ​​\u200b\u200bthe inlet section of the valve.

Vibration . Tapered and tight radii stacks create high back pressure at the outlet and can cause valve vibration. The elimination of this disadvantage is achieved by installing exhaust pipes with a passage not less than the nominal passage of the valve outlet pipe and with a minimum number of bends and turns.

Seizure of moving parts can occur when the valve is not properly assembled or installed due to misalignment and the appearance of lateral forces on the movement parts (spool, stem). Seizures must be removed by machining, and the causes that cause them are eliminated by a qualified assembly.

The valve does not open at the set set pressure:

the spring is incorrectly adjusted - the spring must be adjusted to the specified pressure;

the stiffness of the spring is high - install a spring of lesser stiffness;

increased friction in the guides of the spool - eliminate distortions, check the gaps between the spool and the guide.

The labor protection instruction is the main document that establishes the requirements for the safe performance of maintenance, repair and installation of safety valves.

This manual has been developed in accordance with methodological recommendations taking into account the requirements of legislative and other regulatory legal acts containing state requirements for labor protection, intersectoral labor protection rules (safety rules).

Knowledge of this labor protection instruction for working professions performing maintenance, repair and installation of safety valves is mandatory.

General requirements for labor protection.

This instruction applies to safety valves installed on pressure vessels and process pipelines.

1.1. Persons at least 18 years of age who have passed:

  • medical examination and having no contraindications to admission to this species work;
  • introductory briefing on labor protection and fire safety;
  • primary briefing on labor protection at the workplace;
  • primary briefing on fire safety at the MGP facilities;
  • labor protection training and safe methods and methods of work performance;
  • internship from 2 to 14 shifts;
  • training in the use of PPE;
  • verification of theoretical knowledge of labor protection requirements and practical skills of safe work in the examination committee of the branch for admission to independent work;
  • training and testing knowledge on the provision of first (pre-medical) aid to victims of accidents at work;
  • have studied the requirements of this manual;
  • having a certificate of the established form with a mark on admission to independent work;
  • having a permit to perform gas hazardous work according to the list of GRs;
  • training and having a permit to perform steeplejack work and work at height;
  • trained and licensed to service pressure vessels.
  • The main dangerous and harmful factors affecting the worker at work are:

Table 1

Dangerous and harmful production factors affecting the worker Possible undesirable events in the implementation of production factors (hazards)
1 2
Explosion and fire hazard Injuries and bruises caused by the scattering of equipment elements, pipelines by an employee. Wounds by splinters, details, particles. Lack of oxygen, suffocation.

Four-degree burns:

I - redness of the skin;

II - the formation of bubbles;

III - necrosis of the entire thickness of the skin

Collapsing structures An employee receiving injuries and bruises when structural elements of buildings, walls, structures, scaffolding, stairs, stored materials fall, hit by falling objects and parts (including their fragments and particles). Fractures, wounds, dislocations, bleeding.
Sharp edges, burrs and roughness on the surfaces of workpieces, tools and equipment Getting microtrauma, injury, bleeding, infection
The location of the workplace at a height relative to the surface of the earth (floor) Getting injured and bruised when falling from surfaces different levels as a result of a slip, false step, or trip. Fractures, wounds, dislocations, bleeding
Increased pressure of equipment, pipelines, high pressure in the working area and (or) its abrupt change Injuries and bruises caused by the scattering of equipment elements, pipelines, injuries by fragments, parts, particles by an employee. Wounds, bleeding. Lack of oxygen, suffocation
Increased dust and gas content in the air of the working area Lung diseases, acute or chronic poisoning, shortness of breath, reduced body resistance to infectious diseases, lack of oxygen, suffocation
Increased air pollution of the working area with vapors of flammable and toxic liquids Acute or chronic poisoning, intoxication, disorders nervous system, allergic diseases development of cancer

At mild poisoning- headache, dizziness, palpitations, weakness, mental agitation, causeless lethargy, slight muscle twitching, trembling arms outstretched, muscle cramps

Increased or decreased air temperature of the working area Heat or sunstroke, violation of heat balance, overheating and cooling of the body, violation of the cardiovascular system, violation of water-salt metabolism, colds
Increased noise level in the workplace Hearing damage, partial or complete hearing loss. Neurosis, disruption of the central nervous system, changes in metabolic processes

1.3. To protect against hazardous and harmful production factors, the employee is given certified personal protective equipment (PPE) free of charge, depending on the time of year and working conditions, as well as flushing and neutralizing agents:

  • suit made of heat-resistant anti-static fabric with oil-repellent impregnation with the following protective properties: To - protection against an open flame; Es - protection against electrostatic charges and fields;
  • cotton underwear;
  • leather boots;
  • protective coated gloves.
  • anti-noise headphones

At low temperatures:

  • a suit for protection from low temperatures with a fastened insulating pad made of antistatic heat-resistant fabric impregnated with oil and water;
  • hat with ear flaps;
  • felt boots;
  • insulated mittens or gloves with polymer coated frost-resistant.

To protect the hands of the employee is issued:

Cleansing hand paste, regenerating revitalizing hand cream.

1.4. Works on maintenance, installation and repair of safety valves belong to the category of increased danger and must be carried out in accordance with the list of gas-hazardous works developed in the service with the issuance of a work permit.

1.5. During work, workers and employees are required to comply with the internal labor regulations, work and rest regime established at the enterprise.

1.6. When performing maintenance, installation and repair work on safety valves, a non-sparking tool must be used.

1.7. Employees must know and follow the rules of personal hygiene and sanitation.

1.8 The requirements of this instruction are mandatory. Failure to comply with these requirements is considered as a violation of labor and production discipline and is the basis for bringing the employee to responsibility. All employees performing maintenance, installation and repair of safety valves must familiarize themselves with this instruction against signature.

1.9. The employee is allowed to perform only the work provided for by his labor duties or on behalf of his immediate supervisors, as well as to carry out other lawful actions due to labor relations with the employer or in his interests.

2. Labor protection requirements before starting work.

2.1. The employee is obliged to receive an assignment from the immediate supervisor to perform a certain type of work or certain types of work, to familiarize himself with the content of the task in the journal of daily accounting for the issuance of service tasks against signature.

Performers of maintenance, installation and repair of safety valves must undergo a medical examination by a paramedic.

2.2. Prior to the start of work, all measures to prepare for the conduct of gas hazardous work must be completed. A work permit for carrying out gas hazardous work must be issued and all preparatory work must be completed in accordance with the work permit:

  • conduct targeted training;
  • measure gas contamination before starting work;
  • turn off the gas pipeline section with shut-off valves (according to the attached scheme to the permit);
  • take measures against erroneous or spontaneous rearrangement of stop valves;
  • release gas;
  • post signs “Do not open”, “Do not close”, “Gas hazardous work”;
  • provide the place of work with fire extinguishers OP-10 (2 pcs.).

2.3. Prior to the start of work, employees must be instructed on the safe conduct of work and sign the work permit. Employees must put on overalls, special footwear established in accordance with current standards, check and make sure that the fixed tools and devices are in place and in good condition. It is forbidden to use protective equipment whose test period has expired.

2.4. Under the guidance of the person responsible for the preparation of the workplace, employees must complete all the preparatory activities specified in the work permit. It is also necessary to equip the workplace with primary fire extinguishing equipment in accordance with those specified in the work permit.

2.5. Installation and dismantling at existing installations is allowed only after the complete shutdown of the apparatus and pipelines, and their release from gas.

2.6. The frequency of inspections and repairs of equipment is determined by the operating conditions, features of the equipment and is established by the work instructions drawn up on the basis of the instructions for the repair and operation of manufacturers. The frequency of checking the operation of safety valves on equipment in accordance with STO Gazprom 2-3.5-454-2010 (clause 17.2.35.) at least once a year.

3 Labor protection requirements during work.

3.1. Occupational safety requirements for the installation of safety valves.

3.1.1. Start work after completing the preparatory measures and confirming the possibility of carrying out work by a labor protection engineer, a fire protection engineer and obtaining permission to work from the dispatcher.

When carrying out work:

  • control of gas contamination in the working area after 30 minutes.

3.1.2. To carry out work on the installation of safety valves associated with lifting to a height (1.3 m or more from the surface of the soil or floors), persons with special training in the UKK, trained in safe techniques and methods for the specified type of work, who have mastered the requirements of the "Instructions for labor protection when working at height "No. VR. Immediately before carrying out such work, the work manager is obliged to conduct a target briefing for the workers with an entry in the target briefing log and the signature of the person who conducted the briefing and the persons who received it. When working on the installation of safety valves associated with climbing to a height, the employee must be in special shoes, antistatic overalls, a protective helmet, use a safety belt. To climb to a height, use tested ladders, step ladders. Employees must be informed about the location of the nearest first-aid kit, know and be able to provide first (pre-medical) aid to the victim.

3.1.3. The number of safety valves, their dimensions and throughput must be selected according to the calculation indicated in the passport and operating instructions for process equipment.

3.1.4. Safety valves are installed directly on the vessel / equipment / in a vertical position. If due to the nature of the design of the vessel or the conditions of production, such an installation is not feasible, safety valves should be installed in the immediate vicinity of the vessel on a pipeline or a special offshoot, provided that there is no shut-off device between them and the vessel and monitoring it will not be difficult for persons serving the vessel.

3.1.5. The diameter of the through hole of the inlet fitting on which the valve is installed must be not less than the diameter of the through hole of the connecting flange on the side of the product inlet to the safety valve.

3.1.6 In some cases, a short vertical downpipe vented directly to atmosphere should be used. The diameter of the outlet pipe must not be less than the diameter of the outlet fitting of the valve.

3.1.7. Where this is not possible, drain devices should be used to prevent the accumulation of corrosive media in the valve body. It is not allowed to install locking devices on the discharge and drainage pipes.

3.1.8. Spring valves must be equipped with special lockable caps that close access to the spring adjusting bolts.

3.1.9. Lever relief valve weights must be adjusted and locked onto the lever so that no movement of the weight is possible. Installation of lever-load valves on mobile vessels is not allowed.

3.1.10. The design of safety valves should provide for a device for checking the correct operation of the valve in working condition by forcibly opening it during operation of the vessel, /equipment/

3.1.11. The connecting pipelines of safety valves must be protected from freezing of the working medium in them.

3.1.12. Safety valves installed on technological equipment working under pressure, should not violate its tightness. After installation, the tightness of the installation must be checked using a leak detector, washing the joint or in another way.

3.1.13. The results of the inspection and adjustment must be recorded in the log book. Safety valves operating to discharge the working medium must be provided with means that protect people from exposure to the discharged medium: screens, liquid receivers. Their serviceability is checked before each check of the valve.

3.1.14. Autonomous testing of safety valves for strength by increased pressure and tightness, as well as checking the adjustment of safety valves should be carried out at a specially equipped workplace that provides protection for personnel from active medium emissions and the consequences of destruction of the tested products.

3.2. Occupational safety requirements for the maintenance of safety valves.

3.2.1 Start work after completing preparatory measures and confirming the possibility of performing work by a labor protection engineer, a fire protection engineer and obtaining permission to perform work from the LPUMG dispatcher.

When carrying out work:

  • to control the pressure in the bled area using standard instruments;
  • work according to the schedule of the enterprise in antistatic overalls, special footwear;
  • use PPE of hearing organs;
  • perform work with a serviceable spark-proof tool;
  • the constant presence of a person responsible for the performance of work;
  • availability of fire extinguishing equipment OP-10;
  • gas control after 30 minutes.

3.2.2. All safety valves before putting into operation must be adjusted on a special bench to the set pressure.

3.2.3. Safety valves whose working pressure is up to: 3 kgf / cm² are adjusted to 0.5 kgf / cm² above P working; from Z-x to 60 kgf / cm² are adjusted to 15% more than R working; over 60 kgf / cm² are set to 10% more than P working.

3.2.4. Checking and adjustment of the safety valve must be carried out at least once a year in accordance with the PPR schedule.

3.2.5. Inspection and adjustment of valves must be documented by the appropriate act, the valves are sealed and tagged with the date of adjustment, followed by the date of inspection and adjustment data.

3.3. Occupational safety requirements for the repair of safety valves.

3.3.1. Safety valves installed on equipment, tanks operating under pressure above 0.7 kgf / cm² are subjected to hydraulic test body strength with a pressure equal to the test pressure of the relevant equipment, at each adjustment of the valve.

3.3.2. Work related to the removal and installation of the safety valve on

equipment, refer to gas-hazardous work according to the list of GKS, performed on the basis of a permit for gas-hazardous work, in compliance with all measures to ensure the safety of the work.

3.3.3. Repair and adjustment of safety valves is carried out on a special stand in the room of the instrumentation and A workshop. To ensure safety, when disassembling the safety valve, it is necessary to remove the seal, the safety cap, loosen the spring with a calibration screw and disassemble the safety valve.

3.3.4. During the revision of the safety valve, its spring is thoroughly washed and checked:

  • external inspection to identify surface defects and check the perpendicularity of the ends of the spring axis, while the surface of the spring should not have mechanical damage, dents, nicks, scratches. It is strictly forbidden to throw the spring, hit it:
  • three times compression by a static load that causes maximum deflection, while the spring should not have permanent deformation. The maximum deflection is considered to be such a compression of the spring, in which the gap between the coils in the section of the middle coil of the spring should not exceed 0.1 of the diameter of the spring bar.

3.3.5. The springs are compressed on a manual mechanical stand. The frame of the stand must be limited from the possible ejection of the springs during compression.

3.3.6. All parts of the valve should be cleaned of dirt by washing them in kerosene. After that, inspect to identify defects in the details of the nozzle and spool. Faulty ones should be replaced or restored by machining in order to restore the geometry and remove defective areas, followed by grinding. The lapping of the sealing surfaces of the spool and the nozzle must be carried out separately and especially carefully with special lappings made of cast iron.

3.3.7. The sealing surfaces after grinding them must have a surface that ensures the tightness of the valve seal.

3.3.8. When assembling the safety valve, make sure that the parts of the safety valve are assembled correctly. Before adjusting the spring set pressure, you need to make sure that the spindle does not stick in the guides.

3.3.9. After revision and adjustment, the valve must be sealed, on lever valves the protective cover is sealed.

3.3.10. Each safety valve must be affixed with a 150 x 70 mm metal plate indicating the name of the valve, the pressure to which the valve is set and the date of the next adjustment.

3.3.11. A technical data sheet must be drawn up for each safety valve. The results of the revision and adjustment of the safety valve are recorded in the technical passport.

4.Requirements for labor protection in emergency situations.

4.1. During an accident, the employee must:

  • in the event of a fire, immediately stop work, report a fire by phone, name the address of the facility, the place of the fire, and also give your last name, and proceed to extinguish the fire using the available fire extinguishing equipment;
  • in case of an accident, it is necessary to provide the victim with first aid in accordance with the "Instructions for the provision of first aid in case of accidents", call ambulance and report the incident to the immediate supervisor or head of the service. The place of the accident should be kept unchanged, if this does not endanger the workers and does not lead to an accident.

4.2. If an emergency situation is detected, expressed in a false operation of the valve and pressure is released through the drainage, the employee must:

  • report the malfunction to the person responsible for the management of gas hazardous work;
  • by order of the person responsible for the management of gas hazardous work, make the necessary shutdowns to cut off the equipment on which the safety valve is installed;
  • at the direction of the person responsible for the management of gas hazardous work, after taking the necessary safety measures, proceed with the dismantling, repair and adjustment of the safety valve.

5. Labor protection requirements upon completion of work.

5.1. After completing the installation, repair or maintenance of the safety valve, the personnel must:

  • tidy up the workplace, clean the equipment from contamination;
  • remove tools and fixtures;
  • hand over the workplace, fixtures, tools and protective equipment to the work manager;
  • clean and put special clothes in a special place;
  • take the necessary personal hygiene measures.

5.2. Upon completion of the work, the person responsible for their implementation together with the shift dispatcher must check the quality of their performance, the presence of seals, information plates.

5.3. Check the filling of the technical passport for the safety valve.

5.4. Draw up a safety valve inspection report indicating the setting value, the date of the next valve inspection.

5.5 The work manager, after putting the equipment into working condition, must make a note about the time the work was completed in the work permit.

Safety valves are activated when, for extraordinary reasons, too much pressure is created in the tank. If a safety valve is known to have tripped, then it, like the entire system, should be immediately and thoroughly inspected to determine the cause. In case of operation due to fire, the valve must be replaced.

Safety valves should be inspected each time the tank is filled, but at least once a year. If there is any doubt about the serviceability of the valve, it must be replaced.

Wear eye protection when inspecting pressure relief valves. Never look directly into the pressure relief valve connectors or place any body parts where they may be touched by the pressure relief valve. In some cases, use a flashlight and a small mirror when performing a visual inspection.

To properly inspect the relief valve, check:

  1. Protective cap.Check the protective cap located on the valve or at the end of the pipeline outlet to see what it is protecting. Protective caps help protect the relief valve from possible failure due to rain, sleet, snow, ice, sand, dirt, pebbles, insects, debris, and other contaminants.REPLACE DAMAGED OR MISSING CAPS IMMEDIATELY, KEEP THEM IN STOCK.
  2. Open drainage holes.Dirt, ice, paint, and other foreign particles can interfere with proper flow from the valve body.IF THE DRAINAGE HOLES CANNOT BE CLEANED, REPLACE THE VALVE.
  3. Wear and corrosion of safety valve springs.Frequent exposure to strong concentrations saline solutions, industrial pollution, chemicals and road pollutants can cause metal parts to fail.IF COVERAGE ONRELIEF VALVE SPRING IS CRACKED OR SHUTTERED, REPLACE VALVE.
  4. Mechanical damage.Icing and improper installation can cause mechanical damage.REPLACE VALVE IF THERE IS ANY SIGN OF DAMAGE.
  5. Damage or reconfiguration.Safety valves are set at the factory and operate at a certain pressure.IF THERE IS ANY SIGN OF DAMAGE OR RESETTING, REPLACE VALVE.
  6. Seal seat leakage.Check for leaks in the seat area using a non-aggressive leak detection solution.REPLACE VALVE IF THERE ARE ANY SIGNS OF LEAKING. Never use force to close a leaking safety valve or leave it in service. Forced shut-off can damage the valve and possibly rupture the tank or pipeline in which it is installed.
  7. Corrosion and pollution. REPLACE VALVE IF THERE ARE ANY SIGNS OF CORROSION OR CONTAMINATION ON IT.
  8. Moisture, foreign particles or contamination in the valve.Foreign materials such as paint, resin or ice in safety valve parts can prevent the valves from working properly. Grease that enters the valve body can harden or accumulate dirt, thus interfering with the normal operation of the relief valve. DO NOT ALLOW LUBRICANT TO GET INTO THE VALVE BODY AND IF THERE IS ANY SIGN OF MOISTURE OR FOREIGN MATERIAL INSIDE, REPLACE THE VALVE.
  9. Corrosion or leakage in tank connection.Check the reservoir-valve connection with a non-corrosive leak detection solution. REPLACE THE VALVE IF THERE ARE ANY SIGNS OF CORROSION OR LEAKAGE IN THE CONNECTION BETWEEN THE VALVE AND RESERVOIR.

ATTENTION: Never close the safety valve outlet. Any device that stops a properly functioning safety valve that discharges an over-filled or over-pressurized tank will impair its safe operation!

Replace relief valves at least once every 10 years.

Term safe use safety valves can vary greatly depending on the operating environment. Relief valves must be operated under a wide range of conditions. Corrosion, aging of the elastic seat disc and friction act with different intensity depending on the aggressiveness of the given medium and the intensity of use. Impurities in gases, misuse of the product and incorrect installation may shorten the safe life of the safety valve.

Predicting the safe life of safety valves cannot be accurate. The stresses a valve is subjected to will vary widely and affect its shelf life. In such cases, you can only follow the basic instructions. For example, Liquefied Gas Association Booklet S-1.1 Safety Device Standards - Tanks, section 9.1.1 requires all tanks filled with industrial motor fuels to receive new or unused safety valves after twelve years from the date of manufacture of the tank and every ten years of subsequent service life. The LPG specialist must observe and determine the safe service life of the safety valves in his area. Valve manufacturers can only issue safe lifetime recommendations in the industry.

ATTENTION: The period of use of the safety valve under normal conditions is 10 years from the date of manufacture. But it can be reduced depending on the operating conditions of the valve, then the valve will need to be replaced sooner than in 10 years. It is very important to inspect and maintain safety valves. Failure to properly inspect and maintain safety valves can result in personal injury or property damage.

All Additional Information contained in:

  1. CGA S-1.1 Safety Device Standards - Vessels, Section 9.1.1.
  2. Catalog L-500 ECII.
  3. ESI warning No. 8545-500.
  4. Safety Document NPGA 306, Inspection and Maintenance of LPG Regulators and Valves and LPG Training Guides.
  5. NFPA No. 58 Storage and Handling of Petroleum Gases.
  6. NFPA No. 59, " Liquefied gases in gas plants.
  7. ANSI K61.1 "Safety Requirements for Storage and Handling of Anhydrous Ammonia".

RUSSIAN JOINT STOCK COMPANY OF ENERGY AND ELECTRIFICATION "UES OF RUSSIA"

DEPARTMENT OF DEVELOPMENT STRATEGY AND SCIENTIFIC AND TECHNOLOGICAL POLICY

INSTRUCTIONS FOR ORGANIZING OPERATION, ORDER AND TERMS OF CHECKING SAFETY DEVICES OF BOILERS OF THERMAL POWER PLANTS

RD 153-34.1-26.304-98

Effective from 01.10.99

Developed Open joint-stock company "Firm for adjustment, improvement of technology and operation of power plants and networks ORGRES"

Executor V.B. KACUZIN

Agreed with Gosgortekhnadzor of Russia on December 25, 1997

Approved Department of Development Strategy and Scientific and Technical Policy of RAO "UES of Russia" 22.01.98

First Deputy Chief D.L. BERSENEV

1. GENERAL PROVISIONS

1.1. This Instruction applies to safety devices installed on TPP boilers.

1.2. The instruction contains the basic requirements for the installation of safety devices and determines the procedure for their regulation, operation and maintenance.

Annex 1 sets out the basic requirements for boiler safety devices contained in the rules of the Gosgortekhnadzor of Russia and GOST 24570-81, provides technical characteristics and design solutions for boiler safety devices, recommendations for calculating the throughput of safety valves.

The purpose of the Instruction is to help improve the safety of operation of TPP boilers.

1.3. When developing the Instructions, the governing documents of the Gosgortekhnadzor of Russia, , , , , data on the experience of operating the safety devices of TPP boilers were used.

1.4. With the release of this Instruction lose their force "Instructions for the organization of operation, the procedure and terms for checking the impulse-safety devices of boilers with an operating steam pressure of 1.4 to 4.0 MPa (inclusive): RD 34.26.304-91" and "Instructions for the organization of operation, the procedure and terms for checking pulse-safety devices of boilers with steam pressure above 4.0 MPa: RD 34.26.301 -91 ".

1.5. The Instructions adopted the following abbreviations;

PU- safety device:

PC- safety valve of direct action;

RGPC- Lever-load safety valve of direct action;

PPK- spring-loaded safety valve of direct action;

IPU- impulse safety device;

GIC- main safety valve;

IR- impulse valve;

CHZEM- JSC "Chekhov Power Engineering Plant";

TKZ- Software "Krasny Kotelshchik",

1.6. The method for calculating the throughput of boiler safety valves, forms of technical documentation for safety devices, basic terms and definitions, designs and technical characteristics of safety valves are given in Appendices 2-5.

2. BASIC REQUIREMENTS FOR THE PROTECTION OF BOILERS AGAINST INCREASING PRESSURE OVER THE ALLOWABLE VALUE

2.1. Each steam boiler must be equipped with at least two safety devices.

2.2. As safety devices on boilers with pressure up to 4 MPa (40 kgf / cm 2) inclusive, it is allowed to use:

lever-load safety valves of direct action;

spring operated safety valves.

2.3. Steam boilers with steam pressure over 4.0 MPa (40 kgf / cm 2) must be equipped only with electromagnetically driven impulse safety devices.

2.4. The diameter of the passage (conditional) of lever-load and spring valves of direct action and impulse valves of the IPU must be at least 20 mm.

2.5. The nominal passage of the tubes connecting the impulse valve with the HPC IPU must be at least 15 mm.

2.6. Safety devices must be installed:

a) in steam boilers with natural circulation without a superheater - on the upper drum or dry steamer;

b) in steam once-through boilers, as well as in boilers with forced circulation - on the outlet headers or the outlet steam pipeline;

c) in hot water boilers- on the output manifolds or drum;

d) in intermediate superheaters, all safety devices are on the steam inlet side;

e) in water-switched economizers - at least one safety device at the outlet and inlet of water.

2.7. If the boiler has a non-switchable superheater, a part of safety valves with a capacity of at least 50% of the total capacity of all valves must be installed on the outlet header of the superheater.

2.8. On steam boilers with a working pressure of more than 4.0 MPa (40 kgf / cm 2), impulse safety valves (indirect action) must be installed on the outlet manifold of a non-switchable superheater or on the steam pipeline to the main shut-off body, while for drum boilers for 50% of valves according to the total throughput, steam for impulses must be taken from the boiler drum.

With an odd number of identical valves, it is allowed to take steam for pulses from the drum for at least 1/3 and not more than 1/2 of the valves installed on the boiler.

On block installations, if the valves are located on the steam pipeline directly at the turbines, it is allowed to use superheated steam for the impulses of all valves, while for 50% of the valves an additional electrical impulse must be supplied from a contact pressure gauge connected to the boiler drum.

With an odd number of identical valves, it is allowed to apply an additional electrical impulse from a contact pressure gauge connected to the boiler drum, for not less than 1/3 and not more than 1/2 valves.

2.9. In power units with reheating of steam after the high-pressure cylinder of the turbine (HPC), safety valves with a capacity of at least the maximum amount of steam entering the reheater must be installed. If there is a shut-off valve behind the HPC, additional safety valves must be installed. These valves must be sized to take into account both the total capacity of the pipelines connecting the reheater system to sources of higher pressure not protected by their safety valves at the inlet to the reheat system, and possible steam leaks that may occur if the high pressure pipes of the steam and gas-steam heat exchangers for steam temperature control.

2.10. The total capacity of the safety devices installed on the boiler must be at least the hourly steam output of the boiler.

Calculation of the capacity of the safety devices of boilers in accordance with GOST 24570-81 is given in Appendix 1.

2.11. Safety devices must protect boilers, superheaters and economizers from pressure increase in them by more than 10%. Exceeding the steam pressure when the safety valves are fully opened by more than 10% of the calculated value can be allowed only if this is provided for by the strength calculation of the boiler, superheater, economizer.

2.12. The design pressure of safety devices installed on cold reheat pipelines should be taken as the lowest design pressure for low-temperature elements of the reheat system.

2.13. Sampling of the medium from the branch pipe or pipeline connecting the safety device to the element to be protected is not allowed.

2.14. The installation of shut-off devices on the steam supply line to the safety valves and between the main and impulse valves is not allowed.

2.15. To control the operation of the IPU, it is recommended to use the electrical circuit developed by the Teploelektroproekt Institute (Fig. 1), which provides for normal pressure in the boiler, pressing the plate to the saddle due to the constant flow of current around the winding of the closing electromagnet.

For IPU installed on boilers with a nominal overpressure of 13.7 MPa (140 kgf / cm 2) and below, by decision of the chief engineer of the TPP, it is allowed to operate the IPU without constant current flow around the winding of the closing electromagnet. In this case, the control circuit must ensure that the MC is closed using an electromagnet and turned off 20 s after the MC is closed.

The IR electromagnet control circuit must be connected to backup source direct current.

In all cases, only reversible keys should be used in the control scheme.

2.16. Devices should be installed in the connecting pipes and supply pipelines to prevent sudden changes in wall temperature (thermal shocks) when the valve is actuated.

2.17. The inner diameter of the inlet pipe must not be less than the maximum inner diameter of the inlet pipe of the safety valve. The pressure drop in the supply pipeline to direct-acting safety valves must not exceed 3% of the valve opening pressure. In the supply pipelines of safety valves controlled by auxiliary devices, the pressure drop must not exceed 15%.

2.18. Steam from safety valves must be vented to a safe place. The inner diameter of the discharge pipeline must be at least the largest inner diameter of the outlet pipe of the safety valve.

2.19. The installation of a silencer on the discharge pipeline should not cause a decrease in the throughput of the safety devices below the value required by safety conditions. When equipping the discharge pipeline with a noise suppressor, a fitting for installing a pressure gauge must be provided immediately after the valve.

2.20. The total resistance of the outlet pipelines, including the silencer, must be calculated so that when the medium flow through it is equal to the maximum capacity of the safety device, the backpressure in the valve outlet pipe does not exceed 25% of the response pressure.

2.21. The discharge pipelines of safety devices must be protected from freezing and equipped with drains to drain the condensate accumulating in them. Installation of locking devices on drains is not allowed.

2.22. The riser (vertical pipeline through which the medium is discharged to the atmosphere) must be securely fixed. This must take into account the static and dynamic loads that occur when the main valve is actuated.

2.23. Compensation must be provided in the piping of the safety valves temperature elongations. The fastening of the body and pipeline of safety valves must be calculated taking into account static loads and dynamic forces arising from the operation of safety valves.


Rice. 1. Electrical diagram of the IPU

Note - The scheme is made for one pair of IPK


3. INSTRUCTIONS FOR THE INSTALLATION OF SAFETY DEVICES

3.1. Valve storage rules

3.1.1. Safety devices must be stored in places that exclude moisture and dirt from entering the internal cavities of the valves, corrosion and mechanical damage to parts.

3.1.2. Pulse valves with an electromagnetic drive must be stored in dry closed rooms in the absence of dust and vapors in them that cause the destruction of the windings of the electromagnets.

3.1.3. The shelf life of valves is no more than two years from the date of shipment from the manufacturer. If longer storage is required, the products must be re-preserved.

3.1.4. Loading, transportation and unloading of valves must be carried out with the observance of precautionary measures that guarantee them from breakage and damage.

3.1.5. Subject to the above rules of transportation and storage, the presence of plugs and the absence of external damage, the valves can be installed in the workplace without revision.

3.1.6. If the rules of transportation and storage are not observed, the valves should be inspected before installation. The issue of compliance of the storage conditions of valves with the requirements of the NTD should be decided by a commission of representatives of the operating and repair departments of the TPP and the installation organization.

3.1.7. When inspecting valves, check:

the condition of the sealing surfaces of the valve.

After inspection, the sealing surfaces must be clean. R a = 0.32;

the state of the gaskets;

the condition of the stuffing box packing of the servomotor piston.

If necessary, install a new packing of pre-pressed rings. Based on the tests carried out by ChZEM, for installation in the HPC servo drive chamber, a combined seal can be recommended, consisting of a set of rings: two packs of rings made of graphite and metal foil and several rings made of thermally expanded graphite. (The seal is manufactured and supplied by AOZT "Unihimtek", 167607, Moscow, Michurinsky prospekt, 31, building 5);

the condition of the working piston jacket in contact with the gland packing; traces of possible corrosion damage to the jacket must be eliminated;

the state of the thread of the fasteners (no nicks, scuffs, thread chipping);

condition and elasticity of the springs,

After assembly, check the ease of movement of the moving parts and the compliance of the valve stroke with the requirements of the drawing.

3.2. Placement and installation

3.2.1. Impulse-safety devices must be installed indoors.

The valves may be operated within the following limits environment:

when using valves intended for delivery to countries with a temperate climate: temperature - +40°С and relative humidity - up to 80% at a temperature of 20°С;

when using valves intended for delivery to countries with a tropical climate; temperature - +40°С;

relative humidity - 80% at temperatures up to 27°C.

3.2.2. The products included in the IPU kit must be installed in places that allow their maintenance and repair, as well as assembly and disassembly at the place of operation without cutting out from the pipeline.

3.2.3. Installation of valves and connecting pipelines must be carried out according to the working drawings developed by the design organization.

3.2.4. The main safety valve is welded to the fitting of the manifold or steam line with the stem strictly vertically upwards. The deviation of the stem axis from the vertical is allowed no more than 0.2 mm per 100 mm of the valve height. When welding the valve into the pipeline, it is necessary to prevent the ingress of burrs, splashes, scale into their cavity and pipelines. After welding, the welds are subject to heat treatment in accordance with the requirements of the current instructions for the installation of pipeline equipment.

3.2.5. The main safety valves are fixed with the paws available in the design of the products to the support, which must perceive the reactive forces that occur when the IPU is activated. The valve exhaust pipes must also be securely fastened. In this case, any additional stresses in the connection between the exhaust and connecting flanges of the exhaust pipes must be eliminated. From the bottom point, permanent drainage should be organized.

3.2.6. Impulse dampers for live steam and reheat steam manufactured by LMZ, mounted on a special frame, should be installed on sites that are convenient for maintenance and protected from dust and moisture.

3.2.7. The pulse valve must be mounted on the frame so that its stem is strictly vertical in two mutually perpendicular planes. The IR lever with a load suspended on it and an electromagnet core must not have distortions in the vertical and horizontal planes. To avoid jamming when opening the MC, the lower electromagnet must be located relative to the MC so that the centers of the holes in the core and the lever are on the same vertical; electromagnets must be located on the frame so that the axes of the cores are strictly vertical and are in a plane passing through the axes of the rod and the IR lever.

3.2.8. To ensure a tight fit of the MC plate on the saddle, the bar on which the clamp of the upper electromagnet rests must be welded so that the gap between the lower plane of the lever and the clamp is at least 5 mm.

3.2.9. When taking pulses on the MC and the electrocontact manometer (ECM) from the same element on which the HPC is installed, the places for sampling pulses must be at such a distance from the CHM that, when it is triggered, the perturbation of the steam flow does not affect the operation of the MC and ECM (at least 2 m). The length of the impulse lines between the impulse and main valves must not exceed 15 m.

3.2.10. Electrocontact pressure gauges must be installed at the boiler service mark. Permissible Maximum temperature environment in the EKM installation area should not exceed 60°С. Stop valve on the line for supplying the medium to the ECM during operation must be opened and sealed.

4. PREPARING THE VALVES FOR OPERATION

4.1. The compliance of the installed valves with the requirements is checked project documentation and sec. 3.

4.2. The tightness of the valve fasteners, the condition and quality of the fit of the supporting surfaces of the prism of lever-load valves are checked: the lever and prism must be mated across the entire width of the lever.

4.3. The compliance of the actual magnitude of the GPC stroke with the instructions of the technical documentation is checked (see Appendix 5).

4.4. In the HPC of reheat steam, moving the adjusting nut along the stem provides a gap between its lower end and the upper end of the support disk, equal to the valve travel.

4.5. At CHPK reheat steam manufactured by ChZEM, the screw of the throttle valve built into the cover is turned out by 0.7-1.0 turns,

4.6. The condition of the cores of the electromagnets is checked. They must be cleaned of old grease, rust, dust, washed with gasoline, sanded and rubbed with dry graphite. The rod at the point of articulation with the core and the core itself should not have distortions. The movement of the cores must be free.

4.7. The position of the damper screw of the electromagnets is checked. This screw must be screwed in so that it protrudes above the end of the electromagnet body by about 1.5-2.0 mm. If the screw is fully screwed in, then when the armature is lifted, a vacuum is created under it, and with a de-energized electrical circuit, it is almost impossible to adjust the valve to actuate at a given pressure. Over-driving the screw will cause the core to move violently when retracted, which will break the sealing surfaces of the pulse valves.

5. ADJUSTING THE SAFETY DEVICES TO ACTIVATE AT A GIVEN PRESSURE

5.1. Adjustment of safety devices for operation at a given pressure is carried out:

after the completion of the installation of the boiler;

after a major overhaul, if the safety valves were replaced or overhauled ( complete disassembly, groove of sealing surfaces, replacement of running gear parts, etc.), and for PPK - in case of replacement of the spring.

5.2. To adjust the valves, a pressure gauge with an accuracy class of 1.0 must be installed in the immediate vicinity of the valves, tested in the laboratory against a reference pressure gauge.

5.3. Safety valves are regulated at the workplace of the valve installation by raising the pressure in the boiler to the set pressure.

Adjustment of spring safety valves is allowed to be carried out at the stand with steam with operating parameters, followed by a control check on the boiler.

5.4. Valve actuation during adjustment is determined by:

for IPU - by the moment of operation of the GPC, accompanied by a blow and strong noise;

for full-lift direct-acting valves - by a sharp pop, observed when the spool reaches the upper position.

For all types of safety devices, operation is controlled by the beginning of the pressure drop on the pressure gauge.

5.5. Before adjusting the safety devices, you must:

5.5.1. Make sure that all installation, repair and adjustment works on systems in which the steam pressure necessary for regulation will be created, on the safety devices themselves and on their exhaust pipes.

5.5.2. Check the reliability of disconnecting systems in which pressure will increase from adjacent systems.

5.5.3. Remove all bystanders from the valve adjustment area.

5.5.4. Provide good lighting workstations for the installation of launchers, service platforms and adjacent passageways.

5.5.5. Establish a two-way connection between the valve adjustment points and the control panel.

5.5.6. Instruct shift and adjustment personnel involved in valve adjustment work.

The personnel should be well aware of the design features of the launchers subjected to adjustment and the requirements of the instructions for their operation.

5.6. Adjustment of lever-load valves of direct action is carried out in the following sequence;

5.6.1. The weights on the valve levers move to the end position.

5.6.2. In the protected object (drum, superheater), the pressure is set to 10% higher than the calculated (allowed).

5.6.3. The weight on one of the valves moves slowly towards the body until the valve is actuated.

5.6.4. After closing the valve, the position of the weight is fixed with a locking screw.

5.6.5. The pressure in the protected object rises again and the pressure value at which the valve operates is checked. If it differs from that set in paragraph 5.6.2, the position of the load on the lever is corrected and the correct operation of the valve is rechecked.

5.6.6. After the adjustment is completed, the position of the load on the lever is finally fixed with a locking screw. To prevent uncontrolled movement of the load, the screw is sealed.

5.6.7. An additional weight is placed on the lever of the adjusted valve and the remaining valves are adjusted in the same sequence.

5.6.8. After the adjustment of all valves is completed, the working pressure is established in the protected object. Additional weights are removed from the levers. A record of the readiness of the valves for operation is recorded in the Safety Devices Repair and Operation Log.

5.7. Adjustment of spring-loaded direct acting relief valves:

5.7.1. The protective cap is removed and the spring tightening height h 1 is checked (Table 6).

5.7.2. In the protected object, the pressure value is set in accordance with clause 5.6.2.

5.7.3. By turning the adjusting sleeve counterclockwise, the compression of the spring is reduced to the position at which the valve will actuate.

5.7.4. The pressure in the boiler rises again and the pressure value at which the valve operates is checked. If it differs from that set in accordance with paragraph 5.6.2, then the spring compression is corrected and the valve is rechecked for operation. At the same time, the pressure at which the valve closes is monitored. The difference between the actuation pressure and the closing pressure should be no more than 0.3 MPa (3.0 kgf / cm 2). If this value is greater or less, then it is necessary to correct the position of the upper adjusting sleeve.

For this:

for TKZ valves, unscrew the locking screw located above the cover and turn the damper sleeve counterclockwise - to reduce the difference or clockwise - to increase the difference;

for PPK and SPKK valves of the Blagoveshchensk Valve Plant, the pressure difference between the actuation and closing pressures can be adjusted by changing the position of the upper adjusting sleeve, which is accessed through a hole closed with a plug on the side surface of the body.

5.7.5. The height of the spring in the adjusted position is recorded in the Journal of repair and operation of safety devices and it is compressed to the value h 1 in order to be able to adjust the remaining valves. After the end of the adjustment of all valves on each valve, the height of the spring recorded in the magazine is set in the adjusted position. To prevent unauthorized changes in the tension of the springs, a protective cap is installed on the valve, covering the adjusting sleeve and the end of the lever. The bolts securing the protective cap are sealed.

5.7.6. After the adjustment is completed, a record is made in the Safety Devices Repair and Operation Book about the readiness of the valves for operation.

5.8. Pulse-safety devices with an IR equipped with an electromagnetic drive are regulated for operation both from electromagnets and with de-energized electromagnets.

5.9. To ensure the operation of the IPU from electromagnets, the ECM is configured:

5.9.1. The readings of the EKM are compared with the readings of a standard pressure gauge with a class of 1.0%.

5.9.2. EKM is regulated to turn on the opening electromagnet;

MPa

where h is the correction for water column pressure

MPa

here r is the density of water, kg/m3;

DH - difference between the marks of the place of connection of the impulse line to the protected object and the place of installation of the EKM, m.

5.9.3. EKM is regulated to turn on the closing electromagnet:

MPa.

5.9.4. On the EKM scale, the limits of IR operation are marked.

5.10. The adjustment of the MC for actuation at a given pressure with de-energized electromagnets is carried out in the same sequence as the adjustment of direct-acting lever-weight valves:

5.10.1. The weights on the IR levers are moved to the extreme position.

5.10.2. The pressure in the boiler drum rises up to the setting of the IPU operation ( R cf = 1.1 R b); on one of the IRs connected to the drum of the boiler, the load moves towards the lever to the position at which the IPU will be triggered. In this position, the load is fixed on the lever with a screw. After that, the pressure in the drum rises again and it is checked at what pressure the IPU is triggered. If necessary, the position of the load on the lever is adjusted. After adjustment, the weights on the lever are fastened with a screw and sealed.

If more than one MC is connected to the drum of the boiler, an additional weight is placed on the lever of the adjusted valve in order to be able to adjust the rest of the MCs connected to the drum.

5.10.3. A pressure is set before the CHP, equal to the pressure of operation of the IPU behind the boiler ( R cp = 1.1 R R). In accordance with the procedure provided for in clause 5.10.2, it is regulated for the operation of the IPU, from which the steam at the IR is taken from the boiler.

5.10.4. After the end of the adjustment, the pressure behind the boiler is reduced to the nominal value and additional weights are removed from the IK levers.

5.11. Voltage is applied to electrical circuits IPU management. The valve control keys are set to the "Automatic" position.

5.12. The steam pressure behind the boiler rises to the value at which the IPU should operate, and the opening of the CHP of all IPUs is checked at the place, the impulse to open which is taken behind the boiler.

When adjusting the IPU on drum boilers, the IPU control keys, triggered by an impulse behind the boiler, are set to the "Closed" position and the pressure in the drum rises to the IPU actuation setpoint. The operation of the HPC IPU, operating on an impulse from the drum, is checked locally.

5.13. Impulse-safety devices for reheat steam, behind which there are no shut-off devices, are set to actuate after installation during the heating of the boiler to steam density. The procedure for setting the valves is the same as when setting the live steam valves installed downstream of the boiler (clause 5.10.3).

If it becomes necessary to adjust the pulse valves of the reheat steam after repair, then it can be done on a special stand. In this case, the valve is considered to be adjusted when the rise of the stem by the amount of stroke is fixed.

5.14. After checking the operation of the IPU, the control keys of all IPUs must be in the "Automatic" position.

5.15. After adjusting the safety devices, the shift supervisor must make an appropriate entry in the Journal of the repair and operation of safety devices.

6. PROCEDURE AND TERMS OF CHECKING VALVES

6.1. Checking the correct operation of the safety devices should be carried out:

when the boiler is stopped for scheduled repairs;

during the operation of the boiler:

on pulverized coal boilers - once every 3 months;

on oil-fired boilers - once every 6 months.

During the specified time intervals, the check should be timed to coincide with scheduled shutdowns of the boilers.

On boilers put into operation periodically, the check should be carried out at start-up, if more than 3 or 6 months have passed since the previous check, respectively.

6.2. Checking of fresh steam IPU and reheat steam IPU, equipped with an electromagnetic drive, should be carried out remotely from the control panel with local operation control, and reheat steam IPU, which do not have an electromagnetic drive, by manual detonation of the pulse valve when the unit load is not less than 50% of the nominal.

6.3. Checking the safety valves of direct action is carried out at the operating pressure in the boiler by alternately forced undermining of each valve.

6.4. Checking of safety devices is carried out by the shift supervisor (senior boiler operator) according to the schedule, which is drawn up annually for each boiler based on the requirements of this Instruction, agreed with the operation inspector and approved by the chief engineer of the power plant. After checking, the shift supervisor makes an entry in the Journal of the repair and operation of safety devices.

7. RECOMMENDATIONS FOR MONITORING THE CONDITION AND ORGANIZING THE REPAIR OF VALVES

7.1. Planned condition monitoring (revision) and repair of safety valves are carried out simultaneously with the equipment on which they are installed.

7.2. Checking the condition of safety valves includes dismantling, cleaning and defect detection of parts, checking the tightness of the shutter, the condition of the gland packing of the servo drive.

7.3. Control of the state and repair of valves should be carried out in a specialized valve workshop on special stands. The workshop must be equipped with lifting mechanisms, well lit, have a supply compressed air. The location of the workshop should ensure convenient transportation of the valves to the installation site.

7.4. Control of the condition and repair of valves should be carried out by a repair team with experience in valve repair, who has studied the design features of valves and the principle of their operation. The team must be provided with working drawings of valves, repair forms, spare parts and materials for their quick and high-quality repair.

7.5. In the workshop, valves are disassembled and parts are fault-detected. Before flaw detection, the parts are cleaned of dirt and washed in kerosene.

7.6. When examining the sealing surfaces of the parts of the valve-seat and plate, pay attention to their condition (the absence of cracks, dents, scratches and other defects). During subsequent assembly, the sealing surfaces must be roughened. R a = 0.16. The quality of the sealing surfaces of the seat and plate should ensure their mutual fit, in which the pairing of these surfaces is achieved along a closed ring, the width of which is not less than 80% of the width of the smaller sealing surface.

7.7. When inspecting the servo piston chamber jackets and guides, make sure that the ellipse of these parts does not exceed 0.05 mm per diameter. The roughness of the surfaces in contact with the gland packing must correspond to the cleanliness class R a = 0.32.

7.8. When inspecting the servo piston Special attention should pay attention to the condition of the gland packing. The rings must be tightly pressed together. There must be no damage on the working surface of the rings. Before assembling the valve, it should be well graphitized.

7.9. The thread condition of all fasteners and adjusting screws should be checked. All parts with defective threads must be replaced.

7.10. It is necessary to check the condition of the cylindrical springs, for which purpose to carry out a visual inspection of the surface condition for the presence of cracks, deep scratches, measure the height of the spring in a free state and compare it with the requirements of the drawing, check the deviation of the spring axis from the perpendicular.

7.11. Repair and restoration of valve parts should be carried out in accordance with the current instructions for the repair of fittings.

7.12. Before assembling the valves, check that the dimensions of the parts correspond to the dimensions indicated in the form or working drawings.

7.13. The tightening of stuffing box rings in the piston chambers of the HPC should ensure the tightness of the piston, but not prevent its free movement.

8. ORGANIZATION OF OPERATION

8.1. General responsibility for technical condition, checking and maintenance of safety devices is assigned to the head of the boiler-turbine (boiler) shop, on whose equipment they are installed.

8.2. The order for the workshop appoints persons responsible for checking the valves, organizing their repair and maintenance, and maintaining technical documentation.

8.3. In the workshop, for each boiler, a Journal of repair and operation of safety devices installed on the boiler must be kept.

8.4. Each valve installed on the boiler must have a passport containing the following data;

valve manufacturer;

brand, type or drawing number of the valve;

conditional diameter;

serial number of the product;

operating parameters: pressure and temperature;

opening pressure range;

flow coefficient a equal to 0.9 of the coefficient obtained on the basis of the valve tests;

the estimated area of ​​the flow section;

for spring-loaded safety valves - the characteristics of the spring;

data on the materials of the main parts;

certificate of acceptance and conservation.

8.5. For each group of valves of the same type there must be: Assembly drawing, technical description and instruction manual.

9. SAFETY REQUIREMENTS

9.1. It is forbidden to operate safety devices in the absence of the documentation specified in paragraphs. 8.4, 8.5.

9.2. It is forbidden to operate the valves at pressure and temperature higher than specified in the technical documentation for the valves.

9.3. It is forbidden to operate and test safety valves in the absence of outlet pipes that protect personnel from burns when the valves actuate.

9.4. Impulse valves and valves of direct action must be located in such a way that, during adjustment and testing, the possibility of burns to the operating personnel is excluded.

9.5. It is not allowed to eliminate valve defects in the presence of pressure in the objects to which they are connected.

9.6. When repairing valves, it is forbidden to use wrenches, the size of the "mouth" of which does not correspond to the size of the fasteners.

9.7. All types of repair and maintenance work must be carried out in strict compliance with the requirements of fire safety regulations.

9.8. When the power plant is located in a residential area, the exhaust gases of the HPC IPU must be equipped with noise suppression devices that reduce the noise level when the IPU is triggered to sanitary-permissible standards.

Appendix 1

REQUIREMENTS FOR SAFETY VALVES OF BOILERS

1. Valves must open automatically at a given pressure without fail.

2. In the open position, the valves must operate steadily, without vibration and pulsation.

3. Requirements for direct acting valves:

3.1. The design of a lever-weight or spring-loaded safety valve must be provided with a device for checking the correct operation of the valve during operation of the boiler by forcibly opening the valve.

Forced opening must be possible at 80% of the set pressure.

3.2. The difference between the set pressure (full opening) and the beginning of the valve opening must not exceed 5% of the set pressure.

3.3. Safety valve springs must be protected from direct heat and direct impact working environment.

When the valve is fully opened, the possibility of contact between the coils of the spring must be excluded.

3.4. The design of the safety valve must not allow arbitrary changes in its adjustment during operation. The RGPK on the lever must have a device that excludes the movement of the load. For PPK, the screw that regulates the spring tension must be closed with a cap, and the screws securing the cap must be sealed.

4. Requirements for IPU:

4.1. The design of the main safety valves must have a device that softens the blows when they are opened and closed.

4.2. The design of the safety device must ensure the preservation of the functions of protection against overpressure in the event of failure of any control or regulatory body of the boiler.

4.3. The design of the safety device must allow it to be controlled manually or remotely.

4.4. The design of the device must ensure its automatic closing at a pressure of at least 95% of the working pressure in the boiler,

Annex 2

METHOD OF CALCULATION OF THE CAPACITY OF SAFETY VALVES OF BOILERS

1. The total capacity of all safety devices installed on the boiler must meet the following requirements:

for steam boilers

G 1 + G 2 + ... + GD k;

for hot water boilers

G 1 + G 2 + ... + GQ/g;

Calculation of the capacity of the safety valves of hot water boilers can be performed taking into account the ratio of steam and water in the steam-water mixture passing through the safety valve when it is triggered.

2. The capacity of the safety valve is determined by the formula;

G = 10 AT 1a F (P 1 + 0.1) - for pressure in MPa;

G = AT a F(P 1 + 1) - for pressure in kgf / cm 2,

The values ​​of this coefficient are selected according to the table. 1 and 2 or determined by the formulas.

At pressure P 1 in kgf / cm 2:

Under pressure R 1 in MPa:

Table 1

Coefficient values AT for saturated steam

table 2

Coefficient values AT for superheated steam

Steam pressure R 1 , Coefficient AT at steam temperature t n, °С
MPa (kgf / cm 2) 250 300 350 400 450 500 550 600 650
2,0 (20) 0,495 0,465 0,445 0,425 0,410 0,390 0,380 0,365 0,355
3,0 (30) 0,505 0,475 0,450 0,425 0,410 0,395 0,380 0,365 0,355
4,0 (40) 0,520 0,485 0,455 0,430 0,410 0,400 0,380 0,365 0,355
6,0 (60) 0,500 0,460 0,435 0,415 0,400 0,385 0,370 0,360
8,0 (80) 0,570 0,475 0,445 0,420 0,400 0,385 0,370 0,360
16,0 (160) 0,490 0,450 0,425 0,405 0,390 0,375 0,360
18,0 (180) 0,480 0,440 0,415 0,400 0,380 0,365
20,0 (200) 0,525 0,460 0,430 0,405 0,385 0,370
25,0 (250) 0,475 0,445 0,415 0,390 0,375
30,0 (300) 0,495 0,460 0,425 0,400 0,380

To calculate the capacity of safety valves of power plants with live steam parameters:

13.7 MPa and 560°C AT = 0,4;

25.0 MPa and 550°C AT = 0,423.

The valve capacity formula should only be used if:

- for pressure in MPa;

For pressure in kgf / cm 2,

where R 2 - the maximum overpressure behind the PC in the space into which steam flows from the boiler (when it flows into the atmosphere R 2 = 0),

b is the critical pressure ratio.

For saturated steam b cr = 0.577.

For superheated steam b cr = 0.546.

Annex 3

FORMS OF TECHNICAL DOCUMENTATION ON SAFETY DEVICES OF BOILERS, WHICH SHOULD BE MAINTAINED AT THE TPP

Form No. 1

I approve:

Chief Engineer

______________________

"__" __________ 199__

Vedomosti

operating pressure of the boiler safety devices

in ____________ shop

Foreman ________________

Form No. 2

I approve:

Chief Engineer

______________________

"__" __________ 199__

Carafe for checking boiler safety devices

Number Installed Approximate terms of check of valves
p.p. boiler periodicity 199 199
checks Months Months
1 2 3 4 5 6 7 8 9 10 11 12 1 2 3 4 5 6 7 8 9 10 11 12

Foreman _______________

Note Depending on the duration of the boiler being under repair or in reserve, the terms for checking the valves may be specified.

Form No. 3

Data

on forced testing of boiler safety valves

Form No. 4

Data

on scheduled and emergency repairs of boiler safety valves

Boiler No. _______

Appendix 4

BASIC TERMS AND DEFINITIONS

Based on the operating conditions of TPP boilers, taking into account the terms and definitions contained in various materials of the Gosgortekhnadzor of Russia, GOST and technical literature, the following terms and definitions are adopted in this Instruction.

1. Working pressure R p is the maximum internal overpressure that occurs during the normal course of the working process without taking into account hydrostatic pressure and without taking into account the permissible short-term pressure increase during the operation of the safety devices.

2. Design pressure R calc - excess pressure, which was used to calculate the strength of the elements of the boiler. For TPP boilers, the design pressure is usually equal to the working pressure.

3. Permissible pressure R additional - the maximum overpressure allowed by accepted standards in the protected element of the boiler when the medium is discharged from it through the safety device

R add = 1.1 P p .

Safety devices must be selected and adjusted in such a way that the pressure in the boiler (drum) cannot rise above R add.

4. Start opening pressure R n.o - excess pressure at the inlet to the valve, at which the force directed to open the valve is balanced by the force holding the shut-off body on the seat.

Depending on valve design and process dynamics P n.o \u003d l,03¸l,08 P R. But due to the transience of the process of operation of full-lift safety valves and IPU, when adjusting them, determine P no, practically impossible.

5. Full opening pressure (setting pressure) R cp is the maximum excess pressure that is set in front of the PC when it is fully opened. It must not exceed R add.

6. Closing pressure R h - excess pressure at which, after actuation, the shut-off body is seated on the saddle,

For direct acting safety valves R h = 0.8¸0.9 R R. IPU with electromagnetic drive R h must be at least 0.95 R R.

7. Bandwidth G- maximum mass flow steam that can be vented through a fully open valve at actuation parameters.

Appendix 5

DESIGNS AND TECHNICAL CHARACTERISTICS OF BOILER SAFETY VALVES

1. Live steam safety devices

1.1. Main relief valves

To protect boilers from pressure increase on live steam pipelines, GPC series 392-175 / 95-0 g, 392-175 / 95-0 g -01, 875-125-0 and 1029-200 / 250-0 are used. On old power plants for parameters 9.8 MPa, 540°C, valves of the 530 series are installed, and on blocks of 500 and 800 MW - the E-2929 series, which are currently out of production. At the same time, for the newly designed boilers for parameters 9.8 MPa, 540°C and 13.7 MPa, 560°C, the plant developed a new valve design 1203-150 / 200-0, and for the possibility of replacing exhausted valves series 530 , which had a double-sided steam outlet, the valve 1202-150 / 150-0 is produced.

Specifications produced by CHZEM GPC are given in Table. 3.

Valves of series 392 and 875 (Fig. 2) consist of the following main components and parts: connecting inlet pipe 1, connected to the pipeline by welding; housing 2 with a chamber, which houses the servo 6; plates 4 and saddles 3 constituting the shutter assembly; lower 5 and upper 7 rods; hydraulic damper assembly 8, in the body of which a piston and a spring are placed.

The steam supply in the valve is carried out on the spool. Pressing it to the seat by the pressure of the working medium ensures an increase in the tightness of the shutter. Pressing the plate to the saddle in the absence of pressure under it is provided by a spiral spring placed in the damper chamber.

The 1029-200/250-0 series valve (Fig. 3) is basically similar to the 392 and 875 series valves. The only difference is the presence of a throttle grate in the body and steam removal through two oppositely directed outlet pipes.

Table 3

Technical characteristics of the main safety valves IPU boilers

Valve designation

Nominal diameter, mm steam operating parameters smallest area Flow rate Steam consumption during working Stroke Weight, kg
entrance- output- pressure Tempe-

temperature, °С

on the other on a raft pass-

section, mm 2

parameters, t/h mm
Fresh steam valves
1202-150/150-0 150 150 9,8 540 30,0 17,5 5470 0,5 120 20 415
1203-150/200-0-01 150 200 9,8 540 59,0 17,5 5470 0,5 120 20 345
1203-150/200-0 150 200 13,7 560 59,0 17,5 5470 0,5 165 20 345
392-175/95-0 g-01 175 200 9,8 540 30,0 17,5 4236 0,7 120 22 446
392-175/95-0u 175 200 13,7 560 30,0 20,0 4236 0,7 160 22 446
875-125-0 125 250 25,0 545 80,0 32,0 2900 0,7 240 22 640
1029-200/250-0 150 200 25,0 545 80,0 32,0 11300 0,7 850 28 2252
E-2929 150 200 25,5 560 80,0 32,0 9400 0,7 700 28 2252
Steam reheat valves
111-250/400-0 b 250 400 0,8-1,2 545 9,6 4,5 18700 0,7 50-80 40 727
111-250/400-0 b -0l 250 400 1,3-3,7 545 9,6 4,5 18700 0,7 87-200 45 727
694-250/400-0 250 400 4,1 545 15,0 5,0 18700 0,7 200 45 652
B-7162LMZ 200 400 1,3-3,7 545 9,6 4,5 18700 0,7 87-200 45 590

The valves work as follows:

when opening IR pairs by impulse tube enters the chamber above the servo piston, creating a pressure on it equal to the pressure on the spool. But since the area of ​​the piston, on which the steam pressure acts, exceeds the similar area of ​​the spool, a shifting force occurs, moving the spool down and thereby opening the release of steam from the object. When the pulse valve is closed, steam access to the servomotor chamber is stopped, and the steam present in it is discharged through the drain hole to the atmosphere. At the same time, the pressure in the chamber above the piston drops and due to the action of the medium pressure on the spool and the force of the spiral spring, the valve closes.

To prevent shocks when opening and closing the valve, its design provides for a hydraulic damper in the form of a chamber located in the yoke coaxially with the servo drive chamber. A piston is located in the damper chamber, which is connected to the spool with the help of rods; according to the instructions of the plant, water or some other liquid of similar viscosity is poured or supplied into the chamber. When the valve is opened, fluid flowing through small holes in the damper piston slows down the movement of the valve body and thereby softens the blows. When moving the running gear of the valve in the direction of closing, the same process occurs in the opposite direction 1 . The valve seat is removable, located between the connecting pipe and the body. The seat is sealed with comb metal gaskets. A hole is made in the side of the saddle connected to drainage system, where the condensate accumulated in the valve body after its operation merges. Guide ribs are welded into the connecting pipe to prevent spool vibration and stem breakage.

The peculiarity of valves of the 1202 and 1203 series (Fig. 4 and 5) is that they have a connecting pipe made integral with the body and there is no hydraulic damper, the role of which is played by throttle 8, installed in the cover on the line connecting the over-piston chamber with the atmosphere.

Just like the valves discussed above, valves of the 1203 and 1202 series operate on the principle of "loading": when the IC is opened, the working medium is supplied to the over-piston chamber and when the pressure in it reaches 0.9 R p, starts to move the piston down, opening the discharge of the medium into the atmosphere.

The main parts of live steam valves are made of the following materials: body parts - steel 20KhMFL ​​or 15KhMFL ​​(t> 540 ° C), rods - steel 25Kh2M1F, spiral spring - steel 50KhFA.

The sealing surfaces of the shutter parts are welded with TsN-6 electrodes. Pressed rings made of asbestos-graphite cord of grades AG and AGI are used as stuffing box packing. At a number of thermal power plants, a combined packing is used to seal the piston, which includes rings made of thermally expanded graphite, metal foil, and foil made of thermally expanded graphite. The packing was developed by "UNIKHIMTEK" and was successfully tested on the stands of ChZEM.

1 As the experience of operating a number of TPPs has shown, the valves operate without impact even in the absence of liquid in the damping chamber due to the presence of an air cushion under and above the piston.

Rice. 2. Series 392 and 875 Main Relief Valves:

1 - connecting pipe; 2 - body; 3 - saddle; 4 - plate; 5 - lower rod; 6 - servo drive assembly; 7 - upper rod; 8 - hydraulic damper chamber; 9 - housing cover;

10 - damper piston; 11 - damper chamber cover

Rice. 3. Series 1029 Main Relief Valve

Rice. 4. Series 1202 Main Relief Valve:

1 - body; 2 - saddle; 3 - plate; 4 - servo drive unit; 5 - lower rod; 6 - upper rod;

7 - spring; 8 - throttle

1.2. Pulse valves

All live steam IPUs produced by ChZEM are equipped with pulse valves of the 586 series. The technical characteristics of the valves are given in Table. 4, a constructive solution in fig. 6. The body of the valve - angular, flange connection of the body with a cover. A filter is mounted at the inlet to the valve, designed to trap foreign particles contained in the steam. The valve is actuated by an electromagnetic actuator, which is mounted on the same frame with the valve. To ensure the valve actuation in the event of a power failure in the power supply system of the electromagnets, a load is suspended on the valve lever, by moving which it is possible to adjust the valve to actuate at the required pressure.

Table 4

Specifications for fresh and reheat pulse valves

Valve designation Conditional passage Working environment settings Trial pressure during tests, MPa
(drawing number) D y, mm Pressure, MPa Temperature, °C strength for density Weight, kg
586-20-EM-01 20 25,0 545 80,0 32,2 226
586-20-EM-02 20 13,7 560 80,0 17,5 206
586-20-EM-03 20 9,8 540 80,0 12,5 191
586-20-EMF-03 20 4,0 285 15,0 5,0 198
586-20-EMF-04 20 4,0 545 15,0 5,0 193
112-25x1-OM 25 4,0 545 9,6 4,3 45
112-25x1-0 25 1,2 425 9,6 1,4 31
112-25x1-0-01 25 3,0 425 9.6 3,2 40
112-25x1-0-02 25 4,3 425 9,6 4,3 45

Rice. 5. Series 1203 Main Relief Valve

Rice. 6. Fresh steam pulse valve:

a- valve design; b - valve installation diagram on the frame together with electromagnets

To ensure the minimum inertia of the IPU operation, the impulse valves should be installed as close as possible to the main valve.

2. Impulse-safety devices for reheat steam

2.1. Main relief valves

GPK CHZEM and LMZ are installed on pipelines of cold reheating of boilers D at 250/400 mm. The technical characteristics of the valves are given in Table. 3, constructive solution of the reheat valve CHZEM - in fig. 7. The main components and parts of the valve: body through passage type 1, attached to the pipeline by welding; valve assembly, consisting of a seat 2 and a plate 3, connected by means of a thread to the stem 4; glass 5 with a servo drive, the main element of which is a piston 6 sealed by stuffing box packing; a spring load assembly consisting of two successively arranged helical springs 7, the required compression of which is carried out by a screw 8; throttle valve 9, designed to dampen shock when closing the valve by controlling the rate of steam removal from the over-piston chamber. The saddle is installed between the body and the glass on corrugated gaskets and is crimped when the cover fasteners are tightened. The centering of the spool in the seat is ensured by guide ribs welded to the spool.

Rice. 7. Main Reheat Steam Safety Valves Series 111 and 694:

1 - body; 2 - saddle; 3 - plate; 4 - stock; 5 - glass; 6 - servo piston; 7 - spring; 8 - adjusting screw; 9 - throttle valve; A - steam input from the impulse valve;

B - discharge of steam into the atmosphere

The main parts of the valves are made of the following materials: body and cover - 20GSL steel, upper and lower stems - 38KhMYUA steel, spring - 50KhFA steel, stuffing box packing - AG or AGI cord. The sealing surfaces of the parts of the shutter are welded with TsT-1 electrodes in the factory. The principle of operation of the valve is the same as for live steam valves. The main difference is the way the shock is damped when the valve closes. The degree of shock damping in the GPK steam reheat is controlled by changing the position of the throttle needle and tightening the coil spring.

The 694 series main safety valves for installation in the hot reheat line differ from the 111 series cold reheat valves described above in the material of the body parts. The body and cover of these valves are made of steel 20KhMFL.

The HPC supplied for installation on the cold reheating line, manufactured by PO LMZ (Fig. 8), are similar to CHZEM valves of the 111 series, although they have three fundamental differences:

the sealing of the servo piston is carried out using cast iron piston rings;

valves are equipped with a limit switch that allows you to transfer information about the position of the shut-off element to the control panel;

there is no throttling device on the steam discharge line from the over-piston chamber, which excludes the possibility of adjusting the degree of shock damping or valve closure and, in many cases, contributes to the occurrence of a pulsating valve operation.

Rice. 8. The main safety valve for steam reheating design LMZ

2.2. Pulse valves

Lever-weight valves are used as pulse valves of the IPU CHZEM of the reheat system. D for 25 mm series 112 (Fig. 9, Table 4). The main parts of the valve: body 1, seat 2, spool 3, stem 4, sleeve 5, lever 6, weight 7. The seat is removable, installed in the body and, together with the body, in the connecting pipe. The spool is located in the inner cylindrical bore of the seat, the wall of which plays the role of a guide. The stem transmits force to the spool through the ball, which prevents the valve from tilting when the valve closes. The valve is set to operate by moving the load on the lever and then fixing it in a given position.

Rice. 9. Pulse valve IPU CHZEM reheat steam series 112:

1 - body; 2 - saddle; 3 - spool; 4 - stock; 5 - bushing; 6 - lever; 7 - cargo

Parts are made from the following materials; body - steel 20, stem - steel 25X1MF, spool and seat - steel 30X13.

For valves designed for hot reheating IPU, 112-25x1-OM, the body is made of 12KhMF steel. ChZEM pulse valves for the reheat system are supplied without an electromagnetic actuator, LMZ valves - with an electromagnetic actuator.

3. Valves of direct action PO "Krasny Kotelshchik"

Spring safety valves T-31M-1, T-31M-2, T-31M-3, T-32M-1, T-32M-2, T-32M-3, T-131M, T-132M of the Krasny Production Association boilermaker" (Fig. 10).

Valves spring, full-lift. They have a cast corner body, they are installed only in a vertical position in places with an ambient temperature not higher than +60°C. When the pressure of the medium under the valve increases, the plate 2 is pressed from the seat, and the steam flow, flowing out at high speed through the gap between the plate and the guide sleeve 4, has a dynamic effect on the lifting sleeve 5 and causes a sharp rise of the plate to a predetermined height. By changing the position of the lifting sleeve relative to the guide sleeve, it is possible to find its optimal position, which ensures both a fairly quick opening of the valve and its closing with a minimum pressure drop relative to the operating pressure in the protected system. To ensure minimum steam emission into the environment when the valve is opened, the valve cover is equipped with a labyrinth seal consisting of alternating aluminum and paronite rings. Setting the valve to actuate at a given pressure is carried out by changing the degree of tightening of the spring 6 using the pressure threaded sleeve 7. The pressure sleeve is closed by a cap 8, fixed with two screws. A control wire is passed through the screw heads, the ends of which are sealed.

To check the operation of the valves during the operation of the equipment, a lever 9 is provided on the valve.

The technical characteristics of the valves, overall and connecting dimensions are given in Table. 5.

The valve is currently available with a welded body. The technical characteristics of the valves and the springs installed on them are given in Table. 6 and 7.

Rice. 10. Spring safety valve PO "Krasny Kotelshchik":

6 - spring, 7 - pressure threaded sleeve; 8 - cap; 9 - lever


Table 5

Technical characteristics of spring safety valves, old releases produced by Krasny Kotelshchik

Cipher Diameter Working Maximum Coefficient Least Spring Data Pressure Weight
valve conditional passage, mm pressure, MPa (kgf / cm 2) working environment temperature, °С expense, d flow area F, mm 2 Serial number of the detailed drawing of the spring Wire diameter, mm Spring outer diameter, mm Spring height in free state, mm tightness tests, MPa (kgf / cm 2) valves, kg
T-31M-1 50 3,4-4,5 K-211946 18 110 278 4,5 (45) 48,9
Version 1
T-31M-2 50 1,8-2,8 450 0,65 1960 Execution 2 16 106 276 2,8 (28) 47,6
T-31M-3 50 0,7-1,5 Version 3 12 100 285 1,5 (15) 45,5
T-31M 50 5,0-5,5 K-211948 18 108 279 5,5 (55) 48,3
T-32M-1 80 3,5-4,5 K-211817 22 140 304 4,5 (45) 77,4
Version 1
T-32M-2 80 1,8-2,8 450 0,65 3320 Execution 2 18 128 330 2,8 (28) 74,2
T-32M-3 80 0,7-1,5 Version 3 16 128 315 1,5 (15) 73,4
T-131M 50 3,5-4,0 450 0,65 1960 K-211947

Version 1

18 110 278 4,5 (45) 49,7
T-132M 80 3,5-4,0 450 0,65 3320 K-211817

Version 1

22 140 304 4,5 (45) 80,4

Table 6

Technical characteristics of spring safety valves manufactured by Krasny Kotelshchik Production Association

Valve code

Inlet flange

outlet flange

Limiting parameters of working conditions Estimated diameter, mm / calculated Opening start pressure, MPa ** / kgf / cm 2 Version designation Spring designation Spring tension height Valve weight, kg Flow rate
Nominal diameter, mm Nominal pressure, MPa / kgf / cm 2 Nominal diameter, mm Nominal pressure, MPa / kgf / cm 2 Working pressure, MPa / kgf / cm 2 Medium temperature, °C passage area, mm 2 h 1 mm a
T-31M-1 50 6,4/64 100 1,6/16 Steam 3,5-4,5/35-45 425-350* 48/1810 4.9±0.1/49±1 08.9623.037 08.7641.052-04 200 47,8 0,65
T-31M-2 50 6,4/64 100 1,6/16 -"- 1,8-2,8/18-28 Up to 425 48/1810 3.3±0.1/33±1 08.9623.037-03 08.7641.052-02 200 46,5 0,65
T-31M-3 50 6,4/64 100 1,6/16 -"- 0,7-1,5/7-15 Up to 425 48/1810 1.8±0.1/18±1 08.9623.037-06 08.7641.52 170 44,5 0,65
T-32M-1 80 6,4/64 150 1,6/16 -"- 3,5-4,5/35-45 425-350* 62/3020 4.95±0.1/49.5±1 08.9623.039 08.7641.052-06 210 75,8 0,65
T-32M-2 80 6,4/64 150 1,6/16 -"- 1,8-2,8/18-28 425 62/3020 3.3±0.1/33±1 08.9623.039-03 08.7641.052-04 220 72,11 0,65
T-131M 50 10/100 100 1,6/16 -"- 3,5-4,5/35-45 450 48/1810 4.95±0.1/49.5±1 08.9623.048 08.7641.052-04 200 48,8 0,65
T-132M 80 10/100 150 1,6/16 -"- 3,5-4,5/35-45 450 62/3020 4.9±0.1/49±1 08.9623.040 08.7641.052-06 210 76,1 0,65
* Lower temperature is the limit for higher pressure.
** The limit of factory tests of valves for undermining.

Table 7

Technical characteristics of the springs installed on the valves of the production association "Krasny Kotelshchik"

Geometric dimensions Spring force at working deployed Weight, kg
Designation Outer Diameter Spring height in Step Number of turns working deformation deformation spring length,
springs diameter, mm bar, mm free state, mm windings, mm working n complete n 1 F, kgf(N) springs S 1, mm mm
06.7641.052 27,9 8±0.5 12 340 (3315,4) 3000 2,55
08.7641.052-01 32,7 8±0.3 10 540(5296,4) 3072 4,8
08.7641.052-02 31,5 8±0.3 10 620(6082,2) 2930 4,7
08.7641.052-03 29,0 8±0.3 10 370(3623,7) 3072 4,7
08.7641.052-04 31,5 8±0.3 10 1000(9810) 3000 6,0
08.7641.052-05 36,5 7±0.3 9 1220(11968,2) 2660 5,4
08.7641.052-06 41,7 6.5±0.3 8,5 1560(15308,1) 3250 9,8
08.7641.052-07 41,7 6.5±0.3 8,5 1700(16677) 3300 9,5

List of used literature

1. Rules for the design and safe operation of steam and hot water boilers, - M .: NPO OBT, 1993.

2. GOST 24570-81 (ST SEV 1711-79). Safety valves for steam and hot water boilers. Technical requirements.

3. Instructions for the organization of operation, the procedure and terms for checking pulse-safety devices for boilers with steam pressure above 4.0 MPa: RD 34.26.301-91.- M .: SPO ORGRES, 1993.

4. Instructions for the organization of operation, the procedure and terms for checking the pulse-safety devices of boilers with an operating steam pressure of 1.4 to 4.0 MPa (inclusive): RD 34.26.304-91.- M .: SPO ORGRES. 1993.

5. Impulse-safety devices of the Chekhov plant "Energomash". Technical description and operating instructions.

6. Safety valves JSC "Krasny Kotelshchik". Technical description and operating instructions.

7. GOST 12.2.085-82 (ST SEV 3085-81). Pressure vessels. Safety valves. Safety requirements.

8. Gurevich D.F., Shpakov O.N. Handbook of the designer of pipeline fittings.- L .: Mashinostroenie, 1987.

9. Power fittings for thermal power plants and nuclear power plants. Industry directory-reference book. - M.: TsNIITEITyazhmash, 1991.

1. General Provisions

2. Basic requirements for the protection of boilers from pressure increase above the permissible value

3. Installation instructions for safety devices

4. Preparing valves for operation

5. Adjustment of safety devices for operation at a given pressure

6. Procedure and timing for checking valves

8. Organization of operation

9. Safety requirements

Annex 1. Requirements for boiler safety valves

Appendix 2. Methodology for calculating the capacity of boiler safety valves

Appendix 3. Forms of technical documentation for boiler safety devices, which must be maintained at TPPs

Annex 4. Basic terms and definitions

Appendix 5. Designs and technical characteristics of boiler safety valves

List of used literature

working under pressure

3.4.1. Vessels are subject to protection by safety valves, in which it is possible to exceed the working pressure from the supply source, chemical reaction, heating by heaters, solar radiation, in case of fire near the vessel, etc.

3.4.2. The number of valves, their dimensions and capacity must be be chosen so that the pressure in the vessel cannot exceed 2 design pressure more than 0.05 MPa (0.5 kg/cm) for vessels with 2 pressure up to 0.3 MPa (3 kgf/cm), by 15 percent - for pressure vessels 2 over 0.3 to 6.0 MPa (from 3 to 60 kgf/cm) and by 10 percent - for vessels with 2 pressure over 6.0 MPa (60 kgf/cm).

When the valves are in operation, it is allowed to exceed the pressure in the vessel by no more than 25 percent of the calculated one.

3.4.3. The design and materials of valve elements and their auxiliary devices must ensure the reliable operation of the valve under operating conditions.

3.4.4. The design of the valve must ensure the free movement of the moving elements of the valve and exclude the possibility of their ejection.

3.4.5. The design of the valves and their accessories must exclude the possibility of arbitrary changes in their adjustment.

3.4.6. The design of the valve must exclude the possibility of impermissible shocks during opening and closing.

3.4.7. Valves should be placed in places accessible for convenient and safe maintenance and repair.

When a valve requiring systematic maintenance is located at a height of more than 1.8 m, devices should be provided for ease of maintenance.

3.4.8. Valves on vertical vessels should be installed on the upper bottom, and on horizontal vessels - on the upper generatrix in the gas (steam) phase zone. Valves should be installed in places that exclude the formation of stagnant zones.

3.4.9. The installation of shut-off valves between the vessel and the valve, as well as behind the valve, is not allowed, with the exception of vessels with flammable and explosive substances and substances of the 1st and 2nd hazard classes, as well as for vessels operating at cryogenic temperatures. For such valves, a valve system consisting of a working and reserve valves should be provided.

3.4.10. The working and standby valves must have equal flow capacity, providing complete protection of the vessel from excess pressure above the allowable one. To ensure the revision and repair of valves before and after them, shut-off valves with a blocking device must be installed, which excludes the possibility of simultaneous closing of shut-off valves on the working and reserve valves, and the flow area in the switching unit in any situation must be not less than the flow area of ​​the installed valve.

3.4.11. Valves must not be used to regulate pressure in a vessel or group of vessels.

3.4.12. Lever-load valves may only be installed on stationary vessels.

3.4.13. The design of the cargo and spring valve should provide for a device for checking the correct operation of the valve in working condition by forcibly opening it during the operation of the vessel. Forced opening must be possible at a pressure equal to 80 percent of the set pressure.

It is allowed to install valves without devices for forced opening, if it is unacceptable due to the properties of the working environment (harmful, explosive, etc.) or according to the conditions of the working process. In this case, the valves should be checked periodically within the time limits established by the technological regulations, but at least once every 6 months. subject to the exclusion of the possibility of freezing, sticking, polymerization or clogging of the valve with the working medium.

3.4.14. Valve springs must be protected from impermissible heating (cooling) and direct exposure to the working medium, if it has a harmful effect on the spring material.

3.4.15. The mass of the load and the length of the lever of the lever-weight valve are determined based on the fact that the load is at the end of the lever.

3.4.16. Valves and their ancillaries shall be designed so that, in the event of failure of any control or regulatory body, or power failure to the control valve, the function of protecting the vessel against overpressure by redundancy or other measures is retained.

3.4.17. The design of the valve must provide for the possibility of controlling it manually or remotely.

3.4.18. Electrically actuated valves must be supplied with two independent power supplies. AT electrical diagrams where a power outage causes a pulse to open the valve, one power supply is allowed.

3.4.19. If the control element is a pulse valve, then the nominal diameter of this valve must be at least 15 mm.

3.4.20. The internal diameter of the impulse lines (inlet and outlet) must be at least 20 mm and not less than the diameter of the outlet fitting of the impulse valve. Impulse and control lines must ensure reliable condensate drainage. Install locking devices on these lines is prohibited. It is allowed to install a switching device if, in any position of this device, the impulse line will remain open.

3.4.21. The working medium used to control the valves must not be subject to freezing, coking, polymerization and corrosive effect on the valve material.

3.4.22. The valve must be designed to close at a pressure of at least 95 percent of the set pressure.

3.4.23. The valve must be provided with at least two independently operating control circuits, which must be designed so that if one of the control circuits fails, the other circuit will ensure reliable operation of the valve.

3.4.24. Valves should be installed on branch pipes or pipelines directly attached to the vessel.

When installing several valves on one branch pipe (pipeline), the area cross section branch pipe (pipeline) must be at least 1.25 of the total cross-sectional area of ​​the valves installed on it.

3.4.25. The pressure drop in front of the valve in the supply line at the highest capacity must not exceed 3 percent of the set pressure.

What else to read